Adding stages to schedules
Accountants Enterprise with Practice Manager only
A stage is a series of related tasks grouped around the skill requirements and level of authority of the person or area assigned to complete them.
To add a stage to a schedule
-
Find and open an assignment. See Finding and opening assignments.
-
Select the assignment to which stages are to be added. The Assignment Details page opens.
-
Click the Schedule tab.
-
Select the schedule you want to add stages to from the Schedule drop-down.
-
Click Click here to add a new stage in the first row of the table.
-
Enter the next sequential number in the Step cell.
-
Enter a description in the Stage Description cell. For example, a stage description might be:
-
Commence job and if it is typed as Step 1 the predecessor is None.
-
Preparation and the predecessor is Commence Job (1).
-
Review and the predecessor is Preparation (2).
-
Finalisation and the predecessor is Review (3).
-
Choose the Predecessor from the drop-down. This is the previous stage in the sequence.
-
Press [Enter]. The Status column displays Not started. The remaining columns remain blank.
-
Repeat step 6 and 9 for each stage you are creating.
-
Click OK to save the added stages.