Creating milestones
Accountants Enterprise with Practice Manager only
Milestones are created from Maintenance > Assignment > Milestones.
The Milestones page enables you to add milestones which are then applied to schedules and jobs if required. You can define the name, whether it is shown on the Job Manager — Job Sheet and where it is placed on the planner.
There is only one set of milestones for your practice — and the list of milestones is applicable to all jobs. If a milestone is not applicable to a certain job, the milestone still needs to be completed; otherwise your reporting will be inconsistent.
Available fields
Field | Description |
---|---|
Short Description | This short description is displayed as the column label on the Job Manager — Job Sheet for the milestone. The short description is limited to a maximum of 15 characters. |
Description | This longer description for the milestone may be used in reporting. The description is limited to a maximum of 50 characters. |
Position | This field indicates the position of the milestone on the Job Manager — Job Sheet in order from left to right. Position 1 is the first milestone column on the left. |
Start Milestone | This field is used if the milestone is to be used as a starting milestone. When a milestone tagged as Start Milestone has been completed, the completion date on the Start Milestone is taken as the actual start date. |
End Milestone | This field is used if the milestone is to be used as an ending milestone. When a milestone tagged as End Milestone has been completed, the completion date on the End Milestone is taken as the actual end date. |
Show on Planner | This field indicates whether or not the milestone is shown on the Job Manager — Job Sheet. If this is not selected, the milestone will not be displayed on the Job Manager - Job Sheet. |
Historical reporting may be affected if you deselect a used milestone.
To make use of reporting on milestones, a Start milestone and an End milestone must be flagged. A job is deemed as started when the status of the start milestone is set to Complete. A job is deemed to have ended when the status of the end milestone is set to Complete.
To use reporting on milestones, a start milestone and an end milestone must be flagged for each job. A job is started when the status of the start milestone is set to Complete. A job has ended when the status of the end milestone is set to Complete. When the status of the end milestone is set to Complete, the job/schedule will no longer be displayed on the Job Manager — Job Sheet.